Work has been progressing through the winter on the addition and remodel of the hospital in Tioga, North Dakota.
The initial portion of the project experienced delays caused by utility service relocations, contaminated soils, and steel delivery delays. But since then, sufficient time has been made up to bring the project back on schedule.
The project is adding a 15,000 square foot, two-level clinic, a new ambulance garage, and expanded emergency area to the existing hospital, as well as remodel of the existing facility. The clinic addition will open in July, and the hospital addition/remodel will be complete in early September of this year.